# Chapter 6 — Rollback and Recovery Runbook
|
||||
|
||||
## Purpose
|
||||
|
||||
Document safe, repeatable recovery procedures for the Startup Pricing Service.
|
||||
|
||||
This runbook covers:
|
||||
|
||||
1. Rolling back a healthy production deployment from v2 to v1.
|
||||
2. Recovering from an intentionally failed staging deployment.
|
||||
|
||||
Both procedures must preserve the existing Gitea, Jenkins, Caddy,
|
||||
Prometheus, Grafana, and monitoring infrastructure.
|
||||
|
||||
The application is stateless. No database migration or persistent
|
||||
application data restoration is required.
|
||||
|
||||
## Preconditions
|
||||
|
||||
Before beginning:
|
||||
|
||||
- Confirm that the trusted Jenkins agent and Ansible deployment
|
||||
environment are operational.
|
||||
- Confirm that the previously approved image digests are available
|
||||
in the container registry.
|
||||
- Confirm that the corresponding reviewed deployment configuration
|
||||
commits and release records are available.
|
||||
- Confirm that staging and production HTTPS endpoints are reachable.
|
||||
- Confirm that the operator has authorized deployment privileges.
|
||||
- Record the initial application version, image digest, configuration
|
||||
commit, and deployment timestamp.
|
||||
|
||||
Never use an unverified image tag as a substitute for the recorded
|
||||
immutable repository digest.
|
||||
|
||||
## Scenario 1 — Healthy Production Rollback
|
||||
|
||||
### Objective
|
||||
|
||||
Demonstrate that a working v2 production release can be restored
|
||||
to the previously approved v1 release.
|
||||
|
||||
### Expected Application Behavior
|
||||
|
||||
| Release | Version | Quantity | Expected Total |
|
||||
|---|---|---|---|
|
||||
| v2 | v2 | 3 | USD 36 |
|
||||
| v1 | v1 | 3 | USD 30 |
|
||||
|
||||
### Procedure
|
||||
|
||||
1. Confirm that production is running the approved v2 image digest.
|
||||
2. Verify the production HTTPS `/health` endpoint.
|
||||
3. Verify that `/` reports version v2 and the expected source commit.
|
||||
4. Verify that `/price?quantity=3` returns total 36.
|
||||
5. Record the rollback decision timestamp.
|
||||
6. Retrieve the previously approved v1 image digest and release record.
|
||||
7. Restore the reviewed deployment configuration associated with v1.
|
||||
8. Record the rollback execution start timestamp.
|
||||
9. Execute the Ansible deployment using the v1 production release record.
|
||||
10. Wait for the application health verification to complete.
|
||||
11. Verify the production HTTPS `/health` endpoint.
|
||||
12. Verify that `/` reports version v1 and the original v1 source commit.
|
||||
13. Verify that `/price?quantity=3` returns total 30.
|
||||
14. Confirm that the deployed image digest matches the approved v1 digest.
|
||||
15. Record the successful recovery timestamp.
|
||||
16. Calculate recovery duration and observed service interruption.
|
||||
17. Capture Jenkins, Ansible, HTTPS, and monitoring evidence.
|
||||
|
||||
### Acceptance Criteria
|
||||
|
||||
- Production returns HTTP 200 from `/health`.
|
||||
- Production reports version v1.
|
||||
- Production reports the expected v1 source commit.
|
||||
- Three units cost USD 30.
|
||||
- The deployed image digest matches the approved v1 digest.
|
||||
- Existing infrastructure remains operational.
|
||||
- Recovery duration and service interruption are documented.
|
||||
|
||||
## Scenario 2 — Failed Staging Deployment
|
||||
|
||||
### Objective
|
||||
|
||||
Demonstrate that an invalid deployment configuration is detected
|
||||
and that the service can be restored using a previously reviewed
|
||||
configuration.
|
||||
|
||||
This exercise must run in staging only.
|
||||
|
||||
### Controlled Failure
|
||||
|
||||
Create a separate configuration commit that overrides the
|
||||
application's Gunicorn command:
|
||||
|
||||
```yaml
|
||||
command:
|
||||
- gunicorn
|
||||
- --bind
|
||||
- 0.0.0.0:8001
|
||||
- app:app
|
||||
```
|
||||
|
||||
The container image healthcheck continues to probe port 8000.
|
||||
|
||||
This mismatch should cause the container healthcheck to fail
|
||||
and prevent the deployment from completing successfully.
|
||||
|
||||
### Procedure
|
||||
|
||||
1. Confirm that staging is healthy before the test.
|
||||
2. Record the currently approved staging image digest.
|
||||
3. Record the currently approved staging configuration commit.
|
||||
4. Record the initial staging HTTPS responses.
|
||||
5. Create a separate Git commit containing the controlled port mismatch.
|
||||
6. Deploy the intentionally invalid configuration to staging only.
|
||||
7. Confirm that the container healthcheck fails.
|
||||
8. Confirm that Ansible or Jenkins reports a failed deployment.
|
||||
9. Capture the failure logs, build number, and timestamp.
|
||||
10. Record the recovery decision timestamp.
|
||||
11. Restore the previously reviewed staging configuration.
|
||||
12. Use the previously approved staging release record and image digest.
|
||||
13. Execute the Ansible deployment again.
|
||||
14. Verify that the application becomes healthy.
|
||||
15. Verify the expected version and source commit.
|
||||
16. Verify the correct pricing response.
|
||||
17. Record the recovery completion timestamp.
|
||||
18. Calculate recovery duration and observed interruption.
|
||||
19. Capture Jenkins, Ansible, HTTPS, and monitoring evidence.
|
||||
|
||||
### Acceptance Criteria
|
||||
|
||||
- The intentionally invalid staging deployment is rejected.
|
||||
- The failure is visible in Jenkins or Ansible output.
|
||||
- No production deployment is triggered by the failed staging run.
|
||||
- The previously reviewed configuration is restored.
|
||||
- Staging returns HTTP 200 from `/health`.
|
||||
- The restored application version and source commit are correct.
|
||||
- Pricing behavior matches the restored release.
|
||||
- Recovery duration and service interruption are documented.
|
||||
|
||||
## Recovery Timing
|
||||
|
||||
Record the following timestamps for both scenarios:
|
||||
|
||||
| Measurement | Description |
|
||||
|---|---|
|
||||
| Decision time | When the operator decides to restore the previous release |
|
||||
| Recovery start | When the recovery deployment begins |
|
||||
| Recovery complete | When all required verification checks pass |
|
||||
| Recovery duration | Recovery complete minus recovery start |
|
||||
| Service interruption | Measured period during which the endpoint is unavailable |
|
||||
|
||||
Record actual observations rather than estimated durations.
|
||||
|
||||
If no interruption is observed, report that result and explain
|
||||
the measurement method.
|
||||
|
||||
## Safety Requirements
|
||||
|
||||
- Never run the controlled failure against production.
|
||||
- Never stop or restart the host Docker daemon.
|
||||
- Never remove shared Docker volumes.
|
||||
- Never use `docker compose down -v`.
|
||||
- Never run destructive Docker cleanup commands.
|
||||
- Never modify Gitea, Jenkins, Caddy, or monitoring configurations
|
||||
as part of the controlled failure.
|
||||
- Never rebuild an image during rollback.
|
||||
- Never replace the approved digest with a mutable image tag.
|
||||
- Never silently report a failed deployment as successful.
|
||||
|
||||
## Limitations
|
||||
|
||||
The staging and production environments share one DigitalOcean Droplet.
|
||||
|
||||
Therefore:
|
||||
|
||||
- The environments are logically separated but not physically isolated.
|
||||
- A host failure can affect both environments.
|
||||
- Container recreation can cause temporary service interruption.
|
||||
- The deployment strategy does not guarantee zero downtime.
|
||||
- This exercise does not demonstrate high availability.
|
||||
|
||||
The application is stateless, making image rollback relatively simple.
|
||||
|
||||
For a stateful application, database schema compatibility must also
|
||||
be considered. A backward-compatible expand-and-contract migration
|
||||
strategy would allow older and newer application versions to coexist
|
||||
during a controlled rollback window.
|
||||
|
||||
## Evidence Checklist
|
||||
|
||||
- [ ] Healthy v2 production verification.
|
||||
- [ ] Approved v1 repository digest.
|
||||
- [ ] v1 rollback deployment output.
|
||||
- [ ] Restored v1 production verification.
|
||||
- [ ] Controlled staging configuration commit.
|
||||
- [ ] Failed staging deployment output.
|
||||
- [ ] Restored configuration commit.
|
||||
- [ ] Successful staging recovery output.
|
||||
- [ ] Recovery timestamps and calculations.
|
||||
- [ ] Monitoring screenshots.
|
||||
- [ ] Confirmation that existing infrastructure remains operational.
|
||||
|
||||
## Status
|
||||
|
||||
Runbook prepared.
|
||||
|
||||
Execution, measured results, and supporting evidence remain pending
|
||||
Sergio's implementation and verification.
|
||||